Project Caprock
Aligned Data Centers
A six-building campus just outside Abernathy, in Hale County, not Lubbock County. Aligned says its closed-loop cooling design recirculates the same water and protects the Ogallala Aquifer. Hale County is not among the counties named in the Attorney General's announcement.
Aligned announced a groundbreaking on April 9, 2026. It lists the first facility, LBB-01, as anticipated in service in the first quarter of 2027.
- 540 MWPowerSaid by Aligned Data Centers, April 9, 2026
- 313 acresLandSaid by Aligned Data Centers, April 9, 2026
- 1,650,000 square feetFloor areaSaid by Aligned Data Centers (1.65 million square feet of capacity across six facilities), April 9, 2026
More that has been said
- Cooling
- Liquid cooling with an air-cooled heat rejection system and a closed-loop design that recirculates the same water.Said by Aligned Data Centers, April 9, 2026
Not yet public: water use, water source, water deal or tax break, state permits, state water survey answer
Marker placed near the middle of the county. This is not the site.
Sources
- Aligned Data Centers (press release) · · backs up: announcement, status, power figure, land, water, county, size