Barber Lake site
Cipher Mining (now Cipher Digital)
A site just outside Colorado City where Cipher says its customer Fluidstack will lease the full 300 MW of capacity. Cipher says the plant uses on-site non-potable water only, and the mayor has said the data center is not a city water customer.
San Angelo LIVE reported on Sept. 11, 2026 that the 300 MW campus just outside Colorado City was slated to begin delivering capacity that week. Cipher's Nov. 20, 2025 release describes signed leases and capacity it is developing.
- 300 MWPowerSaid by Cipher Mining (capacity Fluidstack will lease at the site), November 20, 2025
More that has been said
- Cooling
- Closed-loop systems using non-potable water.Said by San Angelo LIVE, September 11, 2026
- Water source
- On-site non-potable water only. Cipher says it will not draw from municipal drinking-water sources, and the mayor has said the data center is not a city water customer.Said by Cipher and Mayor Ruben Hurt, as reported by San Angelo LIVE, September 11, 2026
- Water deal or tax break
- The companies created the Colorado City Infrastructure Fund, a 501(c)(3), to pay for water-system repairs in the town.Said by San Angelo LIVE, September 11, 2026
Not yet public: water use, state permits, state water survey answer
Marker placed at the named town. This is not the site.
Sources
- Cipher Digital (press release) · · backs up: announcement, power figure, location
- San Angelo LIVE · · backs up: status, water, size