| 936-acre rezoning request, Northeast Loop 289WithdrawnLubbockNot yet public: power, water use, cooling, water source, water deal or tax break, state permits, state water survey answer | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Abernathy campus joint ventureProposedNot statedNot yet public: water use, cooling, water source, water deal or tax break, state permits, state water survey answer | Power: 168 MWSaid by TeraWulf (critical IT load for the first phase), October 28, 2025 | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Abilene campus (first phase)OperatingTaylorNot yet public: water use, cooling, water source, water deal or tax break, state permits, state water survey answer | Projected power, full site: 2.1 GWSaid by Crusoe (projected, full Abilene site), March 27, 2026 | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Abilene second campus (900 MW)Under constructionTaylorNot yet public: water use, water source, water deal or tax break, state permits, state water survey answer | Power: 900 MWSaid by Crusoe, March 27, 2026 | –Not yet public | Closed-loop, non-evaporative liquid cooling.Said by Crusoe, March 27, 2026 | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Armstrong County campusProposedArmstrongNot yet public: power, water use, cooling, water source, water deal or tax break, state permits, state water survey answer | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Barber Lake siteUnder constructionMitchellNot yet public: water use, state permits, state water survey answer | Power: 300 MWSaid by Cipher Mining (capacity Fluidstack will lease at the site), November 20, 2025 | –Not yet public | Closed-loop systems using non-potable water.Said by San Angelo LIVE, September 11, 2026 | On-site non-potable water only. Cipher says it will not draw from municipal drinking-water sources, and the mayor has said the data center is not a city water customer.Said by Cipher and Mayor Ruben Hurt, as reported by San Angelo LIVE, September 11, 2026 | The companies created the Colorado City Infrastructure Fund, a 501(c)(3), to pay for water-system repairs in the town.Said by San Angelo LIVE, September 11, 2026 | –Not yet public | –Not yet public |
|---|
| Colchis siteProposedTom GreenNot yet public: water use, cooling, water source, water deal or tax break, state permits, state water survey answer | Power: 1 GWSaid by San Angelo LIVE, describing the planned size, September 21, 2026 | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Duos Edge data center, 18th StreetOperatingLubbockNot yet public: power, water use, cooling, water source, water deal or tax break, state permits, state water survey answer | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Duos Edge data center, AmarilloUnder constructionPotterNot yet public: power, water use, cooling, water source, water deal or tax break, state permits, state water survey answer | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| El Paso data centerUnder constructionEl PasoNot yet public: water use, water source, water deal or tax break, state permits, state water survey answer | Power: 1 GWSaid by Meta, March 26, 2026 | –Not yet public | A closed-loop system that recirculates the same water, with "no operational water use for a majority of the year."Said by Meta, October 15, 2025 | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Frontier campusUnder constructionShackelfordNot yet public: water use, water source, water deal or tax break, state permits, state water survey answer | Power: 1.4 GWSaid by Vantage Data Centers, August 19, 2025 | –Not yet public | A closed-loop chiller system that "requires minimal water."Said by Vantage Data Centers, August 19, 2025 | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Haskell County campusProposedHaskellNot yet public: power, water use, cooling, water source, water deal or tax break, state permits, state water survey answer | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Helios campusOperatingDickensNot yet public: water use, cooling, water source, water deal or tax break, state permits, state water survey answer | Power delivered so far: 133 MW · Power, next phase: 260 MW · Gross power approved and contracted: 800 MWSaid by Galaxy (critical IT load, Phase I; about 200 MW gross) +, July 6, 2026 | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Horizon campusOperatingChildressNot yet public: water use, water source, water deal or tax break, state permits, state water survey answer | Power delivered so far: 50 MW · Power: 750 MWSaid by IREN, as reported by DCD (IT load, first building) +, August 17, 2026 | –Not yet public | Direct-to-chip liquid cooling in each building.Said by DCD, describing the buildings, August 17, 2026 | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Milam County campusProposedMilamNot yet public: power, water use, cooling, water source, water deal or tax break, state permits, state water survey answer | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Project CaprockUnder constructionHaleNot yet public: water use, water source, water deal or tax break, state permits, state water survey answer | Power: 540 MWSaid by Aligned Data Centers, April 9, 2026 | –Not yet public | Liquid cooling with an air-cooled heat rejection system and a closed-loop design that recirculates the same water.Said by Aligned Data Centers, April 9, 2026 | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Project Hyper spur buildings (Jayton)ProposedKentNot yet public: power, water use, cooling, water source, water deal or tax break, state permits, state water survey answer | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Project InfraredProposedLubbockNot yet public: water source, state permits, state water survey answer | Starting power: 6 MW · Maximum power: 27 MWSaid by LEDA President John Osborne, describing Corva's plans +, July 30, 2026 | Water per day: 1,500 gallons a daySaid by Corva, through a closed-loop cooling system, July 30, 2026 | Closed-loop cooling.Said by Corva, as reported by KCBD, July 30, 2026 | –Not yet public | The LEDA board approved an agreement with Corva in June 2026. The terms were not in the reporting we found.Said by KCBD, July 30, 2026 | –Not yet public | –Not yet public |
|---|
| Project Matador (HyperGrid campus)Under constructionCarsonNot yet public: state water survey answer | Power: 11 GWSaid by Fermi America (campus size, "private grid"), October 29, 2025 | Water in a supply agreement, per day (up to): 2,500,000 gallons a daySaid by City of Amarillo final water supply agreement, section 7.01: maximum rate of delivery, "up to," no annual cap stated, October 30, 2025 | Hybrid air and water cooling is planned for the four large power generators, with an estimated 13.2 million gallons a day across the four, according to the Amarillo Tribune's report of Fermi's plans. This is for the generators, not the data halls.Said by Amarillo Tribune, reporting Fermi's plans, October 29, 2025 | City of Amarillo supply: the final agreement sets a maximum delivery of 2.5 million gallons a day and states no annual cap. Fermi is to pay for the wells, piping and other improvements it needs to receive the water.Said by City of Amarillo final water supply agreement, section 7.01, October 30, 2025 | Carson County approved a 10-year tax abatement and reinvestment zone. The Amarillo City Council voted on Oct. 28, 2025 to authorize a 20-year water supply agreement for up to 2.5 million gallons a day, with Fermi paying twice the in-city commercial rate.Said by Fermi America (Carson County); Amarillo Tribune (Amarillo vote), October 29, 2025 | Fermi's release dated Feb. 25, 2026 says the Texas Commission on Environmental Quality gave final approval of an air permit for 6 GW of gas-fired power generation. A permit number was not in the reporting we found.Said by Fermi America, February 25, 2026 | –Not yet public |
|---|
| Site northeast of San AngeloProposedTom GreenNot yet public: power, water use, cooling, water source, water deal or tax break, state permits, state water survey answer | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Texas Critical Data CentersProposedEctorNot yet public: water use, cooling, water source, water deal or tax break, state permits, state water survey answer | Power: 250 MWSaid by Data Center Frontier, describing the joint venture's aim, May 16, 2025 | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public | –Not yet public |
|---|
| Westline site (Dove Creek Technology Campus)ProposedTom GreenNot yet public: power, water use, water deal or tax break, state permits, state water survey answer | –Not yet public | –Not yet public | A closed-loop cooling system.Said by Beacon Data Centers, as reported by San Angelo LIVE, June 2, 2026 | An on-site well for drinking water. Beacon also described removing mesquite trees to free up water and evaluating brackish water with on-site desalination.Said by Beacon Data Centers, as reported by San Angelo LIVE, June 2, 2026 | –Not yet public | –Not yet public | –Not yet public |
|---|