Texas data centers

Data centers in Taylor County, Texas

Taylor County is not on the Texas Attorney General's data center investigation list announced Sept. 24, 2026. Below: the projects we track here, what each has said about water and power, and what to ask.

  • 2projects we track here
  • October 2, 2026last checked

Not on the state's investigation list

Is Taylor County on the state's data center investigation list?

No. Taylor County is not among the 18 counties named on Sept. 24, 2026.

  • A county that is not on the list is not an all-clear. The release says "including," and the Attorney General's office describes the investigation as reaching all data center developments in Texas. This page can only report the counties named on September 24, 2026.
  • List as announced September 24, 2026. Last checked October 2, 2026.

Source: Texas Attorney General, Sept. 24, 2026 announcement

Data center projects in Taylor County

Each project shows what a company or agency has said about water and power, who said it and when, with links to its sources.

OperatingTaylor County · Abilene

Abilene campus (first phase)

Crusoe

The existing Abilene campus. Crusoe puts the projected capacity of the full Abilene site, including the next campus below, at 2.1 GW.

Crusoe said on March 27, 2026 that it had energized the first two buildings in under a year.

  • 2.1 GWProjected power, full siteSaid by Crusoe (projected, full Abilene site), March 27, 2026

Not yet public: water use, cooling, water source, water deal or tax break, state permits, state water survey answer

Marker placed at the named town. This is not the site.

Sources

Under constructionTaylor County · Abilene

Abilene second campus (900 MW)

Crusoe

Two new buildings and an on-site power plant next to the existing Abilene campus. Crusoe says the work is for Microsoft and the cooling is closed-loop and non-evaporative.

Crusoe said land clearing and site preparation were underway on March 27, 2026, with the first building expected to be energized in mid-2027.

  • 900 MWPowerSaid by Crusoe, March 27, 2026

More that has been said

Cooling
Closed-loop, non-evaporative liquid cooling.Said by Crusoe, March 27, 2026

Not yet public: water use, water source, water deal or tax break, state permits, state water survey answer

Marker placed at the named town. This is not the site.

Sources

What to ask your city and county

The same questions work for every project. Start with the checklist, then ask for the records.

Know of a project we are missing?

Send a link to a company release, a government record or a news report. Every entry here needs a source with a date.

Data centers in other Texas counties

On the state's investigation list

Other counties with a project we track

Back to the statewide map

The map, the water and power table for every project, the Lubbock section and the data downloads are on the main page. Texas data centers map

Sources for this page

Last checked: October 2, 2026. Texas Water Code 16.012(m) requires survey recipients to complete and return the Texas Water Development Board's Water Use Survey.

Report an error on this page

Share this page

FacebookEmail

Free to share and print with credit to 806 Connect (CC BY 4.0).